Monday, September 27, 2004

Libary Construction Update

The last part of the expansion's concrete frame will be finished
in the next two weeks. Exterior masonry work is scheduled to
start at the end of this month. Roof steel will go up in
mid-October.

Excavation on the south side of the existing building (to
provide the new utilities to the building) is scheduled to start
in the next couple of weeks. Asbestos abatement in the existing
building was completed last week. Demolition in the existing
building is currently underway and will last about 3 to 4 more
weeks.

Ductwork and plumbing installation is underway on the lower
level of the expansion.

The Upjohn Library Commons will be ready for occupancy in
January '06! Check out the display in Light Fine Arts Lobby!